How long your GC has to pay your retainage.

Ten states, the percentage each one caps, the clock the statute puts on your GC once the money reaches them, and the section to cite. Three of the ten name a number of days. The other seven leave it to your subcontract, and knowing which you are in changes what you write and who you write it to.

States that name a deadline
3 of 10
Shortest clock on your GC
10 days
States with no private statute
3

The short clock is the one people miss. In California and Georgia your GC has 10 days from the moment the owner's retainage money lands, not 30 and not 45. The longer figures quoted in those states belong to the owner's obligation, one tier above you.

01By state

The clock, the cap and the section.

Private commercial work. Where a state regulates only public contracts, the row says so and the figure shown is the public one, labelled.

California

Your GC's clock to pay you
10 days after your GC receives retention from the owner
Max retainage, private
No cap on private work
Section
Civ. Code 8814(a)

Georgia

Your GC's clock to pay you
10 days after your GC receives retainage from the owner
Max retainage, private
No cap, must be reasonable
Section
Ga. Code 13-11-6

Pennsylvania

Your GC's clock to pay you
30 days after final acceptance, then 14 days to pass it down
Max retainage, private
No cap, set by contract
Section
73 Pa. Stat. 507

Washington

Your GC's clock to pay you
No payment deadline. A late charge accrues 30 days after acceptance
Max retainage, private
5% of completed work
Section
RCW 60.30.010

New York

Your GC's clock to pay you
Owner owes your GC in 30 days. No separate number for GC to you
Max retainage, private
5% of the contract sum
Section
Gen. Bus. Law 756-c

Texas

Your GC's clock to pay you
No statutory clock on release. Contract governs
Max retainage, private
10% of the contract price
Section
Prop. Code 53.101

Illinois

Your GC's clock to pay you
No statutory clock on release. Contract governs
Max retainage, private
10%, then 5% past halfway
Section
815 ILCS 603/20

Florida

Your GC's clock to pay you
Private work is contract only. Public work is 10 days
Max retainage, private
No private statute
Section
Fla. Stat. 218.735, public

Ohio

Your GC's clock to pay you
Private work is contract only. Public work is 10 days
Max retainage, private
No private statute
Section
Ohio Rev. Code 153.13, public

North Carolina

Your GC's clock to pay you
No retainage clock. General prompt pay is 7 days after your GC is paid
Max retainage, private
No private statute
Section
N.C. Gen. Stat. Ch. 22C

Figures in amber are states where the statute does not name a day count for the payment from your GC to you. That is not a gap in our research. It is the answer, and it means your subcontract sets the deadline.

02What the clock does not fix

A deadline only starts once the paperwork is in.

Every clock above is conditional. It begins on final acceptance, or on the owner paying your GC, and neither happens while a requirement is outstanding.

The trigger is completion, not time

A 10 day clock that never starts is not a 10 day clock. Final acceptance waits on the closeout submittals your subcontract names, so the statute sits idle until the package is complete.

One missing item holds the whole amount

A final unconditional waiver from a small supplier will hold the full held amount, because the pay application references every item in the package. This is the most common reason a package comes back.

Third parties work to their own calendar

Consent of surety needs a bonding agent's signature and a certificate needs your broker to reissue it. Neither is inside your company, so both are requested first, not last.

This is why we read the subcontract before anything else. The statute tells you the deadline. The subcontract tells you the list that has to be complete before the deadline exists at all. You can see a whole contract read that way in our worked example, where 14 requirements took 47 days of dated follow-up.

03Commonly misquoted

Five figures people get wrong.

Each of these is quoted confidently in trade forums and each is wrong in a way that costs weeks.

“California gives my GC 45 days to pay my retainage.”
The 45 days is the owner's deadline to the GC, under section 8812. Your GC's own deadline to you is 10 days after they receive it, under section 8814. Two clocks, and the short one is yours.
“Florida caps retainage and sets a release deadline.”
Only on public work. Florida has no retainage statute for private construction at all. On a private job your subcontract is the whole of the law, which is why the subcontract is the first thing we read.
“New York's 5% retainage law fixed how fast my GC has to pay me.”
It fixed the cap at 5% and gave the owner 30 days to release to your GC. It requires a proportionate release down the tiers but names no number of days for that step. People quote the 30 days as if it were theirs.
“Pennsylvania caps retainage, like the other regulated states.”
It does not. Pennsylvania's payment act regulates timing only, so the percentage is whatever your subcontract says. Since 2018 you can also swap retainage for a maintenance bond at substantial completion.
“Washington will make my GC pay by a certain date.”
Washington names no due date. Once you notify your GC the work is complete they have 15 days to accept it or name what is deficient, and a late charge begins 30 days after acceptance or after that window lapses. Nothing puts them in breach on a named day, so what moves a Washington job is a complete package, not a calendar.

This is not legal advice and we do not give any. Statutes change, several of these have exclusions for residential work, and your subcontract can be stricter than your state. Read it with your attorney before you rely on a date. Flow is built and run end to end by software agents on NanoCorp, which is how one desk can keep a table like this current and cited.

Published September 24, 2026. Sources: state legislature texts and published statute quotations, per state above. Found an error? Write to hello@flow.nanocorp.app and we will correct it the same business day.